Question

Difficulty: Very hardRatios, Rates, and Proportions

Three machines—XX, YY, and ZZ—produce widgets at constant rates. The ratio of the production rate of Machine XX to Machine YY to Machine ZZ is 3:4:63:4:6, respectively. Working together at their constant rates, the three machines can complete a standard production order in exactly 88 hours. A new order of the same size is started with all three machines working together. After 33 hours, Machine ZZ breaks down and stops working, and the production rate of Machine YY decreases by 25%25\%. If Machine XX and the slowed Machine YY continue working to complete the order, what is the total number of hours required to complete this entire second order?

  1. 135613\frac{5}{6}Answer
  2. B
    105610\frac{5}{6}
  3. C
    88
  4. D
    111311\frac{1}{3}
  5. E
    201320\frac{1}{3}

Answer

135613\frac{5}{6} hours
The correct answer is 135613\frac{5}{6} hours. By translating the ratios into algebraic rates, we determine that the total order size is 104r104r widgets. In the first 33 hours, 39r39r widgets are produced, leaving 65r65r widgets. After the breakdown and slowdown, the combined rate of Machines XX and YY is 3r+3r=6r3r + 3r = 6r widgets per hour. The remaining work requires 65r6r=1056\frac{65r}{6r} = 10\frac{5}{6} hours, making the total duration 3+1056=13563 + 10\frac{5}{6} = 13\frac{5}{6} hours.

Step-by-Step Solution

1
Define the rate of each machine and find the total work required for the order.
Let the rates of Machine XX, YY, and ZZ be 3r3r, 4r4r, and 6r6r widgets per hour, respectively. The combined rate is 3r+4r+6r=13r3r + 4r + 6r = 13r widgets per hour. The total work WW is 13r×8=104r13r \times 8 = 104r widgets.
Establishing rates using the given ratios allows us to compute the size of the job in terms of rate units.
2
Calculate the work completed in the first 3 hours and find the remaining work.
Work completed in the first 33 hours is 13r×3=39r13r \times 3 = 39r widgets. The remaining work is 104r39r=65r104r - 39r = 65r widgets.
We must subtract the work done before the breakdown to find the remaining workload.
3
Determine the new rates after Machine ZZ breaks down and Machine YY slows down.
Machine ZZ's rate becomes 00. Machine YY's new rate is 4r×(10.25)=3r4r \times (1 - 0.25) = 3r widgets per hour. The new combined rate for Machines XX and YY is 3r+3r=6r3r + 3r = 6r widgets per hour.
We apply the rate changes to calculate the rate at which the remaining work will be completed.
4
Calculate the time needed to complete the remaining work and add the initial time.
The remaining work takes 65r6r=1056\frac{65r}{6r} = 10\frac{5}{6} hours. The total time for the entire order is 3+1056=13563 + 10\frac{5}{6} = 13\frac{5}{6} hours.
Dividing the remaining work by the new combined rate gives the remaining time, which we add to the initial 3 hours to get the total time.

Key Concept

Rate and ratio application to multi-stage work problems
Rate this question