A unit of combat engineers can construct a perimeter defense system in hours and minutes. If the commanding officer orders the defense system to be completed in exactly hour and minutes, how many combat engineers in total must be assigned to the task, assuming all engineers work at the same constant rate?
- A16
- B32
- 81Answer
- D89
Answer
81
The problem describes an inverse proportion because decreasing the allotted time requires increasing the number of workers to accomplish the identical task. By converting all times to minutes, the total required work effort is calculated as engineers minutes = engineer-minutes. Dividing this constant work effort by the new strict time constraint of minutes yields the total required personnel: engineers.
Step-by-Step Solution
Key Concept
Inverse Proportions
Estimated Time:1m 30s