When placing and finishing a standard concrete slab, what is the correct chronological sequence of steps from start to finish?
- 1Pour the wet concrete mix evenly into the prepared wooden formwork.
- 2Screed the surface with a straightedge board along the top edges of the forms.
- 3Float the surface with a bull float or hand float to embed coarse aggregate and level ridges.
- 4Cure the slab by keeping it damp or applying a curing compound to allow complete hydration.
Answer
Pouring concrete into forms, screeding with a straightedge, floating the surface, and curing the slab.
Concrete placement follows a logical trade sequence: pouring the material into forms, screeding off excess to establish grade, floating to smooth the paste and embed aggregate, and curing to maintain moisture during the chemical hardening process.
Step-by-Step Solution
Key Concept
Chronological procedure for placing, striking off, smoothing, and curing concrete flatwork.