An industrial textile loom weaves yards of heavy canvas every minutes. Operating at this same constant rate, how many feet of canvas will the loom produce during a complete -hour work shift?
Answer: 540 feet
Answer
540 feet
To solve this problem, you must properly scale a direct proportion while paying careful attention to units. First, harmonize the time units: an 8-hour shift is equal to 480 minutes (8 × 60). Next, set up a proportion or find the scale factor: 480 minutes is exactly 40 times longer than the 12-minute baseline (480 ÷ 12 = 40). Because the loom operates at a constant rate, it will produce 40 times as much canvas. Multiply the 4.5 yards by 40 to find the total yards produced (4.5 × 40 = 180 yards). Finally, the question asks for the answer in feet. Since there are 3 feet in 1 yard, multiply 180 yards by 3 to get exactly 540 feet.
Step-by-Step Solution
Key Concept
Solving multi-step direct proportion problems that require initial and final unit harmonizations (time and length).