A network operations team is preparing to modify BGP path selection attributes across enterprise border routers to optimize traffic flow. Place the steps of the standard change management process in the correct order from initial proposal to final completion.
- 1Submit a detailed Request for Change (RFC) document detailing the proposed BGP modifications, potential business impact, and a clear rollback plan.
- 2Present the RFC to the Change Advisory Board (CAB) for formal review, risk assessment, and deployment authorization.
- 3Validate and test the BGP route policy updates in an isolated lab environment to ensure configuration syntax and expected traffic steering behavior.
- 4Apply the BGP configuration changes to the production border routers during an authorized maintenance window.
- 5Perform post-implementation verification testing and update the official enterprise network configuration baseline documentation.
Answer
The correct operational order for change management is: 1) Submit a detailed Request for Change (RFC) document detailing the proposed BGP modifications, potential business impact, and a clear rollback plan -> 2) Present the RFC to the Change Advisory Board (CAB) for formal review, risk assessment, and deployment authorization -> 3) Validate and test the BGP route policy updates in an isolated lab environment to ensure configuration syntax and expected traffic steering behavior -> 4) Apply the BGP configuration changes to the production border routers during an authorized maintenance window -> 5) Perform post-implementation verification testing and update the official enterprise network configuration baseline documentation.
A structured change management process follows a strict sequence: defining the scope and rollback plan in an RFC, securing stakeholder approval from the CAB, staging and testing in a lab, applying changes during an authorized maintenance window, and concluding with verification and documentation baseline updates.
Step-by-Step Solution
Key Concept
Structured Change Management Lifecycle
Estimated Time:1m 30s