A network operations team is preparing to implement a major infrastructure modification involving the deployment of new interior routing protocol parameters across core enterprise routers. To ensure compliance with IT governance standards, what is the correct chronological sequence of steps the team must follow throughout the standard change management lifecycle?
- 1Draft a formal Request for Change (RFC) defining technical scope, business justification, risk impact analysis, and a detailed backout/rollback procedure.
- 2Submit the RFC for formal review and authorization by the Change Advisory Board (CAB).
- 3Validate the configuration modification in a lab/sandbox environment and schedule an official maintenance window.
- 4Apply the configuration changes to production routers during the maintenance window and execute functional verification tests.
- 5Update configuration baseline documentation, archive updated device state, and conduct a post-implementation review (PIR).
Answer
The correct sequence for standard IT change management is: 1) Draft the RFC including risk analysis and rollback plans, 2) Submit the RFC for CAB review and approval, 3) Perform pre-implementation lab validation and schedule the maintenance window, 4) Execute the change during the maintenance window and perform post-change verification, and 5) Update baseline documentation and conduct a post-implementation review.
Standard ITIL and enterprise change management practices require defining scope and rollback procedures in an RFC prior to obtaining formal CAB authorization. Once approved, changes are validated in a sandbox and scheduled during a low-impact maintenance window. Following execution and verification in production, configuration baselines must be updated and a post-implementation review conducted to finalize the change.
Step-by-Step Solution
Key Concept
Standard Change Management Lifecycle Phases