A network operations team is updating its disaster recovery plan documentation. How should the team arrange the following recovery site solutions in order from shortest Recovery Time Objective (RTO) to longest Recovery Time Objective (RTO)?
- 1Hot site with active-active server cluster and real-time data replication
- 2Warm site with pre-installed network hardware requiring current data backups to be restored
- 3Cold site with physical facility, power, and cooling, but no pre-configured network equipment
Answer
The correct order from shortest to longest RTO is: Hot site with active-active server cluster, followed by Warm site with pre-installed network hardware, and finally Cold site with physical facility only.
A hot site has live data and equipment ready for immediate takeover, providing the shortest RTO. A warm site has infrastructure staged but requires backup data to be restored, resulting in a moderate RTO. A cold site provides only basic environmental controls and space, requiring full hardware provisioning and setup, which results in the longest RTO.
Step-by-Step Solution
Key Concept
Disaster Recovery Site Selection and Recovery Time Objective (RTO)