A network engineering team is drafting a Request for Change (RFC) to deploy automated configuration management scripts across enterprise cloud interconnect routers. Which TWO of the following operational elements must be formally documented within the RFC prior to submitting it to the Change Advisory Board (CAB) for approval?
- A detailed risk assessment and impact analysis identifying business dependencies and potential service disruptions during execution.Answer
- A comprehensive backout plan detailing specific rollback steps and quantifiable metric thresholds that trigger execution if testing fails.Answer
- CResults from deploying and executing the script on production routers prior to CAB review to prove script functionality.
- DA disaster recovery workflow that restores only the most recent incremental configuration file directly without applying the base baseline image.
Answer
The correct elements required in the RFC are a comprehensive risk assessment/impact analysis and a detailed backout plan with predefined rollback triggers.
A formal Request for Change (RFC) submitted to a Change Advisory Board (CAB) must include a thorough risk assessment and impact analysis to quantify potential business disruptions, as well as a rollback plan with explicit metric thresholds defining when to abort and revert the deployment. These components ensure organizational oversight and risk mitigation before production execution.
Step-by-Step Solution
Key Concept
RFC Documentation and CAB Approval Requirements