Question

Difficulty: MediumBusiness Impact Analysis and Business Continuity Management

Match each Business Impact Analysis (BIA) and business continuity metric on the left with its corresponding operational definition in an enterprise airport operations management system on the right.

  • Recovery Point Objective (RPO)The maximum acceptable age of unrecovered transactional data, determining mandatory data backup frequency.
  • Recovery Time Objective (RTO)The target duration of time allowed to restore system hardware, software, and network services back online.
  • Maximum Tolerable Downtime (MTD)The total maximum outage time a critical business process can endure before causing irreversible organizational damage.
  • Work Recovery Time (WRT)The time frame required following technical system restoration to perform integrity checks, testing, and operational reconciliation.

Answer

Recovery Point Objective pairs with acceptable data loss age; Recovery Time Objective pairs with technical system restoration deadline; Maximum Tolerable Downtime pairs with overall outage limit; Work Recovery Time pairs with post-technical restoration operational verification.
Each business continuity metric measures a distinct parameter of operational recovery. RPO measures data loss tolerance (data age). RTO specifies the technical infrastructure restoration target. MTD represents the overall maximum disruption window, and WRT measures post-restoration validation and operational setup before full business resume.

Step-by-Step Solution

1
Map the data loss measurement metric.
RPO corresponds to data loss tolerance measured in time.
RPO dictates how far back in time data recovery must reach (data age).
2
Map the technical infrastructure recovery duration metric.
RTO corresponds to technical service restoration targets.
RTO defines how quickly systems must be powered up and functional.
3
Map the absolute ceiling for organizational disruption.
MTD corresponds to total tolerable process outage duration.
MTD is the threshold beyond which the organization suffers fatal financial or operational harm.
4
Map the post-restoration operational validation phase.
WRT corresponds to verification and data reconciliation time.
WRT spans from technical restoration until business processes are fully operational again.

Key Concept

Business Continuity Metrics and Impact Thresholds
Rate this question