An industrial bakery uses two commercial mixers, Mixer X and Mixer Y, to prepare large batches of dough. Working continuously at its own constant rate, Mixer X can complete 1 full batch of dough in 4 hours. Mixer Y, working continuously at its own constant rate, can complete 1 full batch of dough in 6 hours.
If Mixer X works alone for 1 hour and is then joined by Mixer Y to complete the rest of the batch together, which of the following statements must be true? Select all such statements.
- The remaining of the batch takes 1 hour and 48 minutes for both mixers working together to complete.Answer
- Mixer X completes of the total batch of dough.Answer
- The ratio of the total amount of dough prepared by Mixer X to that prepared by Mixer Y is .Answer
- DBoth mixers working together complete the remaining of the batch in 3 hours and 45 minutes.
- EMixer Y completes of the total batch of dough.
Answer
The correct statements are those indicating that the remaining work takes 1 hour and 48 minutes, Mixer X completes 70% of the batch, and the ratio of work done by Mixer X to Mixer Y is 7 : 3.
The rate of Mixer X is 1/4 batch per hour and Mixer Y is 1/6 batch per hour. In the first hour, Mixer X completes 1/4 of the batch, leaving 3/4 of the batch. Working together, their combined rate is 1/4 + 1/6 = 5/12 batch per hour. The time needed for the remaining 3/4 batch is (3/4) / (5/12) = 1.8 hours, which equals 1 hour and 48 minutes. Mixer X works for a total of 2.8 hours, completing 2.8 / 4 = 0.7 (or 70%) of the batch. Mixer Y works for 1.8 hours, completing 1.8 / 6 = 0.3 (or 30%) of the batch. The ratio of dough prepared by Mixer X to Mixer Y is 0.7 : 0.3 = 7 : 3. Therefore, the statements asserting 1 hour and 48 minutes remaining time, 70% completed by Mixer X, and a 7 : 3 work ratio are all correct.
Step-by-Step Solution
Key Concept
Combined Work Rates and Ratio of Work Completed