A commercial print shop uses two high-speed printing presses, Press Alpha and Press Beta. Press Alpha operates at a constant rate of pages per minute, while Press Beta operates at a constant rate of pages per minute. Press Alpha begins printing a job of pages at 9:00 AM. At 9:15 AM, Press Beta is turned on to assist Press Alpha, and both presses continue printing simultaneously at their respective constant rates until the job is completed. How many total minutes after 9:00 AM will the entire -page job be finished?
Answer: 59 minutes
Answer
The entire 15,000-page job will be finished 59 minutes after 9:00 AM.
Press Alpha operates alone for the first 15 minutes, completing pages. That leaves pages. Once Press Beta joins at 9:15 AM, the combined rate becomes pages per minute. The remaining pages require minutes. Summing the 15-minute initial period and the 44-minute joint period gives a total of 59 minutes after 9:00 AM.
Step-by-Step Solution
Key Concept
Linear work-rate equations with staggered initial start times
Estimated Time:1m 30s