A team of identical excavators working together at a constant rate can clear a parcel of land in . All excavators work together for the first , after which excavators break down and are removed from the site. Assuming the remaining excavators continue working at the same constant rate, how many additional days will it take to complete the clearing of the land?
- Answer
- B
- C
- D
Answer
The correct answer is .
The total work required for the project is excavator-days. During the first days, the excavators complete excavator-days of work, leaving excavator-days of work remaining. Since excavators break down, excavators remain. The additional time needed for these excavators to clear the rest of the land is days.
Step-by-Step Solution
Key Concept
Inverse proportion and work-rate problem involving partial completion and workforce changes.