A contractor estimates that workers, working per day, can complete a road construction project in . All workers work at the same constant rate. After working for , workers leave the site. To make up for the loss, the daily working duration for each remaining worker is increased to per day. However, due to fatigue, the work efficiency of each remaining worker drops by . How many additional days will be required to complete the remaining work?
Answer: 25 days
Answer
It will take 25 additional days to complete the remaining work.
The total project requires worker-hours (). In the first days, worker-hours are completed, leaving worker-hours. After workers leave, workers remain. Working hours a day at efficiency, the workers produce effective worker-hours each day. Dividing the remaining worker-hours by gives exactly additional days.
Step-by-Step Solution
Key Concept
Compound Proportion and Work Efficiency