The table below shows the distribution of weekly overtime hours worked by technicians in a manufacturing plant:
| Overtime Hours () | 2 | 4 | 6 | 8 |
|---|---|---|---|---|
| Number of Technicians () | 4 | 3 | 2 | 1 |
What is the variance of the overtime hours?
- 4Answer
- B2
- C1.6
- D4.4
Answer
The variance of the overtime hours is .
The correct answer is . First, compute the mean . Then compute the sum of weighted squared deviations . Dividing this by total frequency yields .
Step-by-Step Solution
Key Concept
Variance for Frequency Distributions
Estimated Time:1m 30s