A building contractor agrees to construct a commercial cold room facility for a food processing firm. After completing approximately 60% of the construction strictly according to the agreed specifications, the food processing firm wrongfully repudiates the contract and orders the contractor off the site. If the contractor chooses not to sue for total breach of contract damages but instead seeks payment for the proportion of work already executed, which legal remedy should the contractor claim?
- Quantum meruitAnswer
- BSpecific performance
- CInjunction
- DRescission
Answer
Quantum meruit is the appropriate remedy because it compensates the injured party for the actual value of work performed up to the point of wrongful repudiation.
Quantum meruit (meaning 'as much as he has earned') is a remedy available when an innocent party has performed part of an entire contract and is wrongfully prevented from completing the rest by the other party. The innocent party is entitled to recover reasonable payment for the portion of work already completed.
Step-by-Step Solution
Key Concept
Quantum Meruit as a Remedy for Breach of Contract
Estimated Time:1m 30s