A highway construction company is contracted to pave a new road. In the first month, they complete exactly of the total project length. In the second month, they pave of the *remaining* length. If there are exactly kilometers left to pave in the third month to finish the project, what is the total length of the highway in kilometers?
- 84Answer
- B80
- C63
- D504
Answer
The total length of the highway is 84 kilometers.
The total length of the highway is 84 km. In the first month, is completed, leaving . In the second month, of this remaining is completed, which means of the remainder is left for the third month. Calculating this relative to the total: . Since of the total project equals 21 km, the total length must be km.
Step-by-Step Solution
Key Concept
Converting recurring and terminating decimals to fractions and computing successive remainders.
Estimated Time:1m 30s