An engineering unit is excavating a rectangular trench that is yards long, yards wide, and feet deep. The excavated dirt will be removed using dump trucks. If each dump truck has a rectangular bed that measures feet long, feet wide, and feet deep, what is the total number of truckloads required to remove all the dirt from the trench?
- A81
- B9
- 27Cevap
- D243
Cevap
27
To find the number of truckloads, the total volume of the trench must be divided by the volume of one truck, ensuring all measurements use the same unit. Converting all dimensions to yards, the truck volume is cubic yards, and the trench volume is cubic yards. Dividing by yields exactly truckloads.
Adım Adım Çözüm
Anahtar Kavram
Calculating and comparing volumes of rectangular prisms while performing correct unit conversions between standard linear measurements.