Following an unexpected power outage, a system administrator replaces a damaged internal power supply on a high-availability network storage unit. The unit boots cleanly into the management dashboard. To adhere strictly to Step 5 (Verify full system functionality and, if applicable, implement preventive measures) of the CompTIA troubleshooting methodology, which of the following actions should the administrator perform? (Select TWO.)
- Execute a synthetic storage stress test and monitor volume I/O to ensure system stability under load.Cevap
- Connect the storage unit to an online uninterruptible power supply (UPS) and verify power redundancy policies.Cevap
- CDocument the incident root cause, replacement component details, and resolution time in the ticketing system.
- DRe-assign IP address leases on the network switch using Layer 2 DHCP scope properties.
Cevap
The administrator should execute a synthetic storage stress test to confirm load stability and connect the storage unit to an online UPS while verifying power redundancy policies.
Verifying full system functionality requires testing the system under realistic operational stress to ensure stability. Implementing preventive measures involves configuring hardware redundancy, such as an uninterruptible power supply (UPS), to safeguard against future power disruptions.
Adım Adım Çözüm
Anahtar Kavram
CompTIA 6-Step Troubleshooting Methodology (Step 5: Verification & Preventive Measures)