A network technician needs to upgrade the firmware on a campus access switch following standard IT service management practices. In what chronological order should the technician execute the steps of the change management lifecycle from first to last?
- 1Draft and submit a formal Request for Change (RFC) detailing the change scope, risk analysis, and rollback procedure.
- 2Obtain formal authorization and scheduling clearance from the Change Advisory Board (CAB).
- 3Execute the firmware installation and perform initial verification during the approved maintenance window.
- 4Conduct a post-implementation review (PIR) to confirm change success and update configuration baselines.
Cevap
The correct sequence starts with submitting the RFC, followed by securing CAB approval, deploying the update during the maintenance window, and concluding with a post-implementation review.
Standard change management follows a strict lifecycle: initiating an RFC with impact and rollback details, obtaining formal CAB authorization, implementing the change within an approved maintenance window, and concluding with a post-implementation review to verify success and document the updated baseline.
Adım Adım Çözüm
Anahtar Kavram
Standard Change Management Lifecycle