An e-commerce enterprise is planning to migrate its on-premises relational database to Cloud SQL for MySQL with minimal operational downtime using GCP Database Migration Service (DMS). Place the following database migration steps in the correct chronological execution order from first to last.
- 1Provision the target Cloud SQL instance and apply the database schema definitions.
- 2Configure continuous Change Data Capture (CDC) replication job parameters in Database Migration Service.
- 3Execute the initial full baseline data snapshot migration from the source database to Cloud SQL.
- 4Stop application write traffic to the source database, verify zero CDC replication lag, and switch application endpoints to Cloud SQL.
Cevap
The correct execution order is: 1) Provision the target Cloud SQL instance and apply database schema definitions, 2) Configure continuous Change Data Capture (CDC) replication job parameters in Database Migration Service, 3) Execute the initial full baseline data snapshot migration from the source database to Cloud SQL, 4) Stop application write traffic to the source database, verify zero CDC replication lag, and switch application endpoints to Cloud SQL.
The correct sequence follows standard database migration best practices: first provision destination resources and schema, then establish CDC replication pipelines, perform the initial baseline bulk load, and finally pause write traffic to verify zero replication lag before switching application connection strings.
Adım Adım Çözüm
Anahtar Kavram
Minimal-Downtime Database Migration Cutover Sequencing