Soru

Zorluk: ZorDesigning Migration Plans and Data Transfer Strategies

A healthcare enterprise needs to migrate 1.5 PB1.5\text{ PB} of historical medical imaging archives from an on-premises data center to Google Cloud Storage within a strict deadline of 30 days30\text{ days}. The organization has an existing 1 Gbps1\text{ Gbps} Dedicated Interconnect link, but baseline daily operations consistently consume 80%80\% of its total bandwidth capacity. Corporate security governance mandates that all migrated data must be encrypted using Customer-Managed Encryption Keys (CMEK). Which data transfer strategy should you recommend to meet both the operational constraints and completion timeline?

  1. Order GCP Transfer Appliance devices to perform an offline bulk data copy on-premises, ship the devices to Google for ingestion into Cloud Storage, and apply CMEK encryption during bucket setup.Cevap
  2. B
    Configure Storage Transfer Service to perform an online data migration over the existing Dedicated Interconnect connection using parallel agent pools.
  3. C
    Provision multiple high-throughput HA VPN tunnels over the public internet to bypass the bandwidth constraints of the existing Dedicated Interconnect link.
  4. D
    Stage the dataset in public Cloud Storage buckets via gsutil over the internet, relying exclusively on IAM roles for data protection without configuring VPC Service Controls.

Cevap

Order GCP Transfer Appliance devices to transfer the petabyte-scale data offline to Cloud Storage, and secure the ingested data using Customer-Managed Encryption Keys (CMEK).
For petabyte-scale datasets (1.5 PB1.5\text{ PB}) where usable network bandwidth is restricted to 200 Mbps200\text{ Mbps}, online network transfer would take over 23 months. Utilizing Transfer Appliance allows secure offline capture and rapid physical delivery, satisfying both the 30-day migration timeframe and CMEK security compliance requirements.

Adım Adım Çözüm

1
Calculate usable network bandwidth throughput for online transfer.
The usable bandwidth on the 1 Gbps1\text{ Gbps} line is 20%20\%, which equals 200 Mbps200\text{ Mbps} (25 MB/s25\text{ MB/s}).
Baseline operational workloads take up 800 Mbps800\text{ Mbps} of the available 1 Gbps1\text{ Gbps} capacity.
2
Calculate time required to transfer 1.5 PB1.5\text{ PB} over the network.
Transferring 1.5 PB1.5\text{ PB} (1,500,000 GB1,500,000\text{ GB}) at 25 MB/s25\text{ MB/s} requires approximately 60,000,000 seconds60,000,000\text{ seconds} (~694 days694\text{ days}).
Network-based online transfer cannot complete within the required 30 day30\text{ day} window.
3
Select the appropriate data migration product for offline petabyte-scale data.
Choose GCP Transfer Appliance, which physically ingests 1.5 PB1.5\text{ PB} of data locally and is shipped directly to Google Cloud data centers for fast upload.
Transfer Appliance bypasses WAN bandwidth limitations and comfortably meets the 30-day timeline requirement while supporting CMEK integration.

Anahtar Kavram

Selecting between online network transfer (Storage Transfer Service) and offline physical transfer (Transfer Appliance) based on dataset size, available bandwidth, and completion timelines.