Soru

Zorluk: ZorWork Rate and Combined Work

A specialized express freight facility uses three automated sorting systems—System 1, System 2, and System 3—to process incoming shipments. Operating continuously at their respective constant rates, System 1 and System 2 working together can process 1 full shipment in 6 hours; System 2 and System 3 working together can process the same shipment in 10 hours; and System 1 and System 3 working together can process the shipment in 7.5 hours. Processing begins with System 1 and System 2 working together. After 3 hours, System 1 breaks down and stops operating, at which point System 3 is immediately activated to work alongside System 2 until the entire shipment is completed. How many total hours does it take, from the start of processing, to complete the entire shipment?

Cevap: 8 hours

Cevap

The total time required from start to completion is 8 hours.
Converting completion times to work rates per hour gives paired rates of 1/6, 1/10, and 2/15. Summing these and dividing by 2 yields a combined three-system rate of 1/5 shipment per hour. In the first 3 hours, System 1 and System 2 complete 3 * (1/6) = 1/2 of the shipment. System 2 and System 3 then finish the remaining 1/2 at their combined rate of 1/10 per hour, requiring (1/2) / (1/10) = 5 hours. Total elapsed time is 3 + 5 = 8 hours.

Adım Adım Çözüm

1
Set up equations for the rate of work done per hour by each pair of systems
Let r1,r2,r3r_1, r_2, r_3 be the individual work rates in shipments per hour. Then r1+r2=16r_1 + r_2 = \frac{1}{6}, r2+r3=110r_2 + r_3 = \frac{1}{10}, and r1+r3=17.5=215r_1 + r_3 = \frac{1}{7.5} = \frac{2}{15}.
Work rate is inversely proportional to completion time (Rate=WorkTimeRate = \frac{Work}{Time}).
2
Calculate the combined processing rate of all three systems
2(r1+r2+r3)=16+110+215=5+3+430=1230=252(r_1 + r_2 + r_3) = \frac{1}{6} + \frac{1}{10} + \frac{2}{15} = \frac{5 + 3 + 4}{30} = \frac{12}{30} = \frac{2}{5}, which simplifies to r1+r2+r3=15r_1 + r_2 + r_3 = \frac{1}{5} shipment per hour.
Adding the three paired rates accounts for each individual system's rate exactly twice.
3
Determine the amount of work completed during the initial 3-hour period
Work completed = 3 hours×(r1+r2)=3×16=123 \text{ hours} \times (r_1 + r_2) = 3 \times \frac{1}{6} = \frac{1}{2} of the total shipment.
System 1 and System 2 operate together at a combined rate of 16\frac{1}{6} shipment per hour for 3 hours.
4
Calculate the time needed for System 2 and System 3 to complete the remaining shipment
Remaining work = 112=121 - \frac{1}{2} = \frac{1}{2}. Time required = 1/2r2+r3=1/21/10=5\frac{1/2}{r_2 + r_3} = \frac{1/2}{1/10} = 5 hours.
System 2 and System 3 work together at a combined rate of 110\frac{1}{10} shipment per hour to finish the remaining half of the job.
5
Calculate the total time elapsed from start to finish
Total time = 3 hours+5 hours=8 hours3 \text{ hours} + 5 \text{ hours} = 8 \text{ hours}.
The question asks for the total duration of the process from the beginning.

Anahtar Kavram

Solving systems of simultaneous work rate equations and analyzing multi-stage combined work.
Bu soruyu puanla