Soru

Zorluk: OrtaWork Rate and Combined Work

Two automated document redaction pipelines, Pipeline AA and Pipeline BB, process digital legal archives. Working alone at its constant rate, Pipeline AA can redact a standard archive in 88 hours. Working alone at its constant rate, Pipeline BB can redact the same standard archive in 1212 hours. Both pipelines begin processing a standard archive together. After 33 hours of joint operation, Pipeline AA encounters a system error and stops. Pipeline BB continues working alone at its constant rate until the entire archive is redacted. How many total hours does it take from start to finish to complete the redaction of the archive?

Cevap: 7.5 hours

Cevap

The total time required to redact the entire archive from start to finish is 7.5 hours.
To find the total time required, first determine the combined rate of Pipeline A and Pipeline B: 18+112=524\frac{1}{8} + \frac{1}{12} = \frac{5}{24} archive per hour. In the first 3 hours of joint work, they complete 3×524=583 \times \frac{5}{24} = \frac{5}{8} of the job, leaving 158=381 - \frac{5}{8} = \frac{3}{8} of the archive remaining. Pipeline B processes the remaining 38\frac{3}{8} at its individual rate of 112\frac{1}{12} per hour, taking 3/81/12=4.5\frac{3/8}{1/12} = 4.5 hours. Adding the initial 3 hours to the 4.5 additional hours yields a total of 7.5 hours.

Adım Adım Çözüm

1
Determine the individual work rate for each pipeline.
Pipeline A's rate is 18\frac{1}{8} archive per hour; Pipeline B's rate is 112\frac{1}{12} archive per hour.
Work rate is the fraction of job completed per hour (1/time required alone1 / \text{time required alone}).
2
Calculate the combined work rate during joint operation.
Combined rate is 18+112=524\frac{1}{8} + \frac{1}{12} = \frac{5}{24} archive per hour.
When entities work concurrently, their rates are added together.
3
Determine the amount of work completed in the first 3 hours.
Work completed is 3×524=583 \times \frac{5}{24} = \frac{5}{8} of the total archive.
Work done equals rate multiplied by time.
4
Find the fraction of the archive remaining to be redacted.
Remaining work is 158=381 - \frac{5}{8} = \frac{3}{8} of the archive.
The full task represents 1 complete unit of work.
5
Calculate how long Pipeline B needs to finish the remaining work alone.
Solo time for Pipeline B is 3/81/12=4.5\frac{3/8}{1/12} = 4.5 hours.
Time equals remaining work divided by Pipeline B's individual rate.
6
Sum the joint operation time and the solo operation time.
Total time is 3+4.5=7.53 + 4.5 = 7.5 hours.