A pharmaceutical facility uses two automated purification columns, Column XX and Column YY, to process standard batches of a synthetic compound. Working alone at its constant rate, Column XX can purify a full batch in 1515 hours, while Column YY can purify a full batch in 1010 hours working alone at its constant rate. Column XX begins purifying a batch alone. After 33 hours, Column YY is turned on to work alongside Column XX, and both columns work together at their respective constant rates until the batch is completely purified. What is the total time, in hours, from the moment Column XX started until the batch is completely purified?

  1. A
    4.8 hours
  2. B
    7.2 hours
  3. 7.8 hoursCevap
  4. D
    9.6 hours
  5. E
    11.0 hours

Cevap

7.8 hours
The correct answer of 7.8 hours is obtained by evaluating the work completed in stages. In the first 3 hours, Column X completes 3/15 or 1/5 of the batch, leaving 4/5 of the batch remaining. When Column Y joins Column X, their combined rate is 1/15 + 1/10 = 1/6 batch per hour. Completing the remaining 4/5 of the batch at a rate of 1/6 per hour requires (4/5) / (1/6) = 4.8 hours. Adding the initial 3 hours yields a total time of 7.8 hours.

Adım Adım Çözüm

1
Determine the individual hourly work rates for each column
Rate of Column X=115X = \frac{1}{15} batch per hour; Rate of Column Y=110Y = \frac{1}{10} batch per hour.
Work rate is the reciprocal of total time required to complete one full job.
2
Calculate the fraction of work completed during the initial stage
Work done by X=3×115=315=15X = 3 \times \frac{1}{15} = \frac{3}{15} = \frac{1}{5} of the batch.
Column XX works alone for the first 3 hours.
3
Find the remaining fraction of work to be completed
Remaining work =115=45= 1 - \frac{1}{5} = \frac{4}{5} of the batch.
Subtract the completed fraction from the total job (1 full batch).
4
Determine the combined work rate of both columns working together
Combined rate =115+110=230+330=530=16= \frac{1}{15} + \frac{1}{10} = \frac{2}{30} + \frac{3}{30} = \frac{5}{30} = \frac{1}{6} batch per hour.
Rates add when two entities work simultaneously.
5
Calculate the time required for both columns to finish the remaining work
Time together =Remaining WorkCombined Rate=4/51/6=45×6=245=4.8= \frac{\text{Remaining Work}}{\text{Combined Rate}} = \frac{4/5}{1/6} = \frac{4}{5} \times 6 = \frac{24}{5} = 4.8 hours.
Time equals work divided by rate.
6
Calculate the total elapsed time from the start
Total time =3 hours (alone)+4.8 hours (together)=7.8= 3 \text{ hours (alone)} + 4.8 \text{ hours (together)} = 7.8 hours.
Add the initial duration to the combined working duration.

Anahtar Kavram

Work Rate and Combined Work