Soru

Zorluk: ZorWork Rate and Combined Work

Scanner Unit Alpha and Scanner Unit Beta, operating independently at their respective constant rates, can complete a document digitization project together in 1212 hours. Scanner Unit Alpha operates at a rate that is 50%50\% faster than that of Scanner Unit Beta. The project is carried out in three consecutive stages: first, Scanner Unit Alpha operates alone for 44 hours; second, Scanner Unit Beta joins Alpha and both operate together until 70%70\% of the entire project is completed; finally, Scanner Unit Beta finishes the remaining portion of the project alone. How many total hours does it take to complete the entire digitization project?

Cevap: 19 hours

Cevap

The total time required to complete the entire digitization project is 19 hours.
To find the total time needed, calculate the individual rates first. With a combined rate of rA+rB=112r_A + r_B = \frac{1}{12} and rA=1.5rBr_A = 1.5 r_B, solving 2.5rB=1122.5 r_B = \frac{1}{12} yields rB=130r_B = \frac{1}{30} and rA=120r_A = \frac{1}{20}. During Stage 1 (44 hours), Alpha completes 4×120=0.204 \times \frac{1}{20} = 0.20 of the job. In Stage 2, both units work together to bring completion from 20%20\% to 70%70\% (0.500.50 work), taking 0.501/12=6\frac{0.50}{1/12} = 6 hours. In Stage 3, Beta completes the remaining 0.300.30 work alone, taking 0.301/30=9\frac{0.30}{1/30} = 9 hours. Summing all stage durations yields 4+6+9=194 + 6 + 9 = 19 hours.

Adım Adım Çözüm

1
Determine the individual work rates of Scanner Unit Alpha (rAr_A) and Scanner Unit Beta (rBr_B).
rB=130r_B = \frac{1}{30} project per hour, and rA=120r_A = \frac{1}{20} project per hour.
Since their combined rate is 112\frac{1}{12} project per hour and rA=1.5rBr_A = 1.5 r_B, we solve 2.5rB=1122.5 r_B = \frac{1}{12} to find rB=130r_B = \frac{1}{30} and rA=120r_A = \frac{1}{20}.
2
Calculate the fraction of work completed during Stage 1.
Scanner Unit Alpha completes 0.200.20 (20%20\%) of the project in 44 hours.
Alpha works alone for 44 hours at a rate of 120\frac{1}{20} project per hour: 4×120=0.204 \times \frac{1}{20} = 0.20.
3
Calculate the duration of Stage 2 where both units work together.
Stage 2 takes 66 hours.
The combined units must complete the portion from 20%20\% to 70%70\%, which represents 0.700.20=0.500.70 - 0.20 = 0.50 of the project. At a combined rate of 112\frac{1}{12} project per hour, the time required is 0.501/12=6\frac{0.50}{1/12} = 6 hours.
4
Calculate the duration of Stage 3 where Scanner Unit Beta works alone.
Stage 3 takes 99 hours.
Beta must complete the remaining 30%30\% (0.300.30) of the project alone. At a rate of 130\frac{1}{30} project per hour, the time required is 0.301/30=9\frac{0.30}{1/30} = 9 hours.
5
Sum the durations of all three stages to determine total project time.
Total time = 1919 hours.
Adding the duration of each stage: 4 hours+6 hours+9 hours=19 hours4 \text{ hours} + 6 \text{ hours} + 9 \text{ hours} = 19 \text{ hours}.

Anahtar Kavram

Work Rate and Combined Work
Bu soruyu puanla