Soru

Zorluk: Çok zorFractions and Rational Numbers

In a manufacturing facility, three automated machines—Machine A, Machine B, and Machine C—produce components at constant individual rates. Machine A working alone completes 310\frac{3}{10} of a standard daily order in 33 hours. Machine B working alone completes 25\frac{2}{5} of the order in 66 hours. Machine C working alone completes 14\frac{1}{4} of the order in 55 hours.

Initially, all three machines work together for 33 hours. At the end of 33 hours, Machine A malfunctions and stops, while Machines B and C continue working together without interruption until the daily order is finished. How many total hours does it take from the start to complete the entire daily order?

Cevap: 6 hours

Cevap

The total time required from the start to complete the entire daily order is 6 hours.
Each machine's rate per hour is found by dividing the given fraction by hours: Machine A is 110\frac{1}{10}, B is 115\frac{1}{15}, and C is 120\frac{1}{20}. Summing these gives an initial combined rate of 1360\frac{13}{60} per hour. In the first 3 hours, the three machines complete 3×1360=13203 \times \frac{13}{60} = \frac{13}{20} of the order, leaving 11320=7201 - \frac{13}{20} = \frac{7}{20} of the order remaining. When Machine A stops, the remaining combined rate of B and C is 115+120=760\frac{1}{15} + \frac{1}{20} = \frac{7}{60} per hour. Dividing the remaining 720\frac{7}{20} by 760\frac{7}{60} yields 3 additional hours. Adding the initial 3 hours gives a total duration of 6 hours.

Adım Adım Çözüm

1
Determine individual hourly work rates for each machine.
Machine A rate = 110\frac{1}{10} order/hr, Machine B rate = 115\frac{1}{15} order/hr, Machine C rate = 120\frac{1}{20} order/hr.
Divide the fraction of the job completed by the duration in hours to find the unit rate for each machine.
2
Calculate the combined rate of all three machines and the fraction completed in the first 3 hours.
Combined rate = 1360\frac{13}{60} order/hr; Work completed in 3 hours = 1320\frac{13}{20}, leaving 720\frac{7}{20} of the order unfinished.
Sum the three rates using a common denominator of 60, then multiply by 3 hours to find the total work done during the first stage.
3
Calculate the combined rate of Machines B and C, and find the additional time required to complete the remaining fraction.
Combined rate of B and C = 760\frac{7}{60} order/hr; Additional time needed = 3 hours.
Divide the remaining fraction 720\frac{7}{20} by the combined rate 760\frac{7}{60} to determine the remaining hours needed.
4
Add the initial duration and additional duration to obtain the total time.
Total time = 3+3=63 + 3 = 6 hours.
The question asks for the total elapsed time from the start of the job.

Anahtar Kavram

Adding rational fractions with different denominators to solve multi-stage work and rate problems.
Bu soruyu puanla