With reference to the Environmental Impact Assessment (EIA) Notification, 2006 in India, consider the following statements:
1. Category 'A' projects require mandatory environmental clearance at the central level by the Ministry of Environment, Forest and Climate Change (MoEFCC) based on recommendations of the Expert Appraisal Committee (EAC).
2. Category 'B1' projects are appraised at the state level by the State Level Environment Impact Assessment Authority (SEIAA) and undergo mandatory Environmental Impact Assessment and public consultation.
3. Category 'B2' projects are strictly required to conduct a public hearing and submit a detailed Environmental Impact Assessment report prior to clearance.
Which of the statements given above is/are correct?
- 1 and 2 onlyCevap
- B1 and 3 only
- C2 and 3 only
- D1, 2 and 3