A mason is constructing a standard concrete masonry unit (CMU) block wall on a cured concrete footing. Arrange the following construction steps in their correct chronological order from first to last.
- 1Spread a full mortar bed joint along the chalk line on the concrete footing.
- 2Set, level, and plumb the corner lead blocks at each end of the wall.
- 3Fasten and tension a mason's line between the corner leads.
- 4Butter head joints and lay intermediate stretcher blocks to the guide line.
- 5Strike and compact the mortar joints with a jointer once thumbprint hard.
Answer
The correct sequence is: (1) Spread a full mortar bed joint on the footing, (2) Set, level, and plumb corner lead blocks, (3) Fasten and tension a mason's line between the corner leads, (4) Butter head joints and lay intermediate stretcher blocks, and (5) Strike and compact the mortar joints once thumbprint hard.
Constructing a CMU block wall follows a strict trade sequence: first, spreading the mortar bed on the footing provides the base; second, setting and leveling the corner leads establishes height and vertical plumb; third, pulling a taut mason's line provides the horizontal guide; fourth, buttering and laying stretcher blocks completes the course; and fifth, striking joints when thumbprint hard seals the mortar against moisture.
Step-by-Step Solution
Key Concept
Concrete Masonry Unit (CMU) Wall Construction Sequence