An engineering battalion is tasked with laying tons of asphalt to repair a section of an airfield runway. By the end of the first week, they have completed of the total required amount. How many tons of asphalt do they still need to lay to complete the repair?
Answer: 1470 tons
Answer
1470
The correct answer is found by determining the remaining percentage of the total project. If of the work is completed, then remains. To find the exact tonnage, calculate of tons by converting the percentage to a decimal and multiplying: .
Step-by-Step Solution
Key Concept
Calculating the remaining percentage of a whole quantity
Estimated Time:1m 0s