A senior systems administrator has completed the initial documentation for an upcoming enterprise database server migration. The administrator defined the scope of the change, documented the business purpose, conducted a comprehensive risk analysis, and created a detailed rollback plan. Which of the following actions should the administrator perform NEXT in accordance with standard change management procedures?
- Submit the proposed change request package to the Change Advisory Board (CAB) for review and approval.Answer
- BPerform post-implementation testing on the live production cluster to verify system performance.
- CExecute the documented rollback plan in the production environment to ensure system recovery works.
- DNotify end users immediately that the database system will be offline for maintenance in 15 minutes.
Answer
Submitting the proposed change request package to the Change Advisory Board (CAB) for review and approval is the mandatory next step.
In standard ITIL and CompTIA change management frameworks, once a change request package (including scope, risk analysis, business purpose, and rollback plan) is drafted, it must be submitted to the Change Advisory Board (CAB) for formal review and approval. Approval ensures that business impact, resource availability, and risk mitigation strategies are validated prior to scheduling and execution.
Step-by-Step Solution
Key Concept
Change Management Workflow Order (Plan → Risk/Rollback → CAB Approval → Notification → Implementation → Testing)