Question

Difficulty: MediumWork Rate and Combined Work

A commercial bakery uses two automated dough mixing machines, Machine AA and Machine BB, to process large batches of dough. Working alone at its constant rate, Machine AA can process a full batch of dough in 1212 hours. Machine BB, working alone at its constant rate, can process a full batch of dough in 66 hours. Machine AA starts processing a batch alone. After working for 33 hours, Machine BB joins Machine AA, and both machines work together at their respective constant rates to finish the batch. What is the total number of hours required to process the entire batch of dough from start to finish?

Answer: 6 hours

Answer

The total number of hours required to process the entire batch of dough from start to finish is 6 hours.
Machine A processes 1/12 of the batch per hour. In the first 3 hours, Machine A finishes 3/12 = 1/4 of the batch, leaving 3/4 of the batch uncompleted. When Machine B joins, the combined processing rate is 1/12 + 1/6 = 1/4 batch per hour. Dividing the remaining 3/4 batch by the combined rate of 1/4 batch per hour yields 3 hours. Adding the initial 3 hours worked by Machine A alone gives a total elapsed time of 6 hours.

Step-by-Step Solution

1
Determine the individual work rates for Machine AA and Machine BB.
Machine AA's rate is 112\frac{1}{12} batch/hour, and Machine BB's rate is 16\frac{1}{6} batch/hour.
Work rate is the fraction of the job completed per hour (1 divided by total hours required alone).
2
Calculate the portion of the batch completed by Machine AA operating alone during the first 3 hours.
Machine AA completes 3×112=312=143 \times \frac{1}{12} = \frac{3}{12} = \frac{1}{4} of the batch.
Work completed equals work rate multiplied by time worked.
3
Determine the remaining fraction of the batch to be completed.
Remaining work is 114=341 - \frac{1}{4} = \frac{3}{4} of the batch.
The entire job corresponds to 1 whole batch.
4
Calculate the combined work rate of Machine AA and Machine BB.
Combined rate =112+16=112+212=312=14= \frac{1}{12} + \frac{1}{6} = \frac{1}{12} + \frac{2}{12} = \frac{3}{12} = \frac{1}{4} batch per hour.
When machines work together, their individual rates add up.
5
Calculate the time required for both machines working together to complete the remaining work.
Time together =Remaining WorkCombined Rate=3/41/4=3= \frac{\text{Remaining Work}}{\text{Combined Rate}} = \frac{3/4}{1/4} = 3 hours.
Time equals work divided by rate.
6
Calculate the total time required from start to finish.
Total time =3 hours (Machine A alone)+3 hours (both together)=6= 3 \text{ hours (Machine A alone)} + 3 \text{ hours (both together)} = 6 hours.
The total time is the sum of time spent in each phase of the process.

Key Concept

Work Rate and Combined Work
Rate this question