A municipal water treatment facility utilizes three primary purification units—Unit P, Unit Q, and Unit R—to process large water batches. Operating alone at its constant rate, Unit P can process a full batch in hours, Unit Q can process a full batch in hours, and Unit R can process a full batch in hours. All three units begin processing a batch together. After hours, Unit P stops operating due to scheduled maintenance. Unit Q and Unit R continue operating together for an additional hours, after which Unit Q is shut down. Unit R then completes the remainder of the batch working alone. How many total hours does it take from start to finish to process the complete batch?
Answer: 17 hours
Answer
The total time required to process the complete batch from start to finish is 17 hours.
To find the total time from start to finish, analyze the work completed in each of the three stages:
1. In Stage 1 (3 hours), all three units operate together. Their combined rate is batch per hour. In hours, they complete of the total batch.
2. In Stage 2 (2 hours), Unit P stops and Units Q and R continue together. Their combined rate is batch per hour. In hours, they complete of the total batch.
3. After Stage 2, the total fraction of work completed is of the batch. The remaining fraction of work is of the batch.
4. In Stage 3, Unit R completes the remaining batch alone at its rate of batch per hour. The time taken by Unit R is hours.
Adding the durations of all three stages gives total hours.
1. In Stage 1 (3 hours), all three units operate together. Their combined rate is batch per hour. In hours, they complete of the total batch.
2. In Stage 2 (2 hours), Unit P stops and Units Q and R continue together. Their combined rate is batch per hour. In hours, they complete of the total batch.
3. After Stage 2, the total fraction of work completed is of the batch. The remaining fraction of work is of the batch.
4. In Stage 3, Unit R completes the remaining batch alone at its rate of batch per hour. The time taken by Unit R is hours.
Adding the durations of all three stages gives total hours.
Step-by-Step Solution
Key Concept
Combined Work Rate in Multi-Stage Work Scenarios