An engineer battalion is excavating a rectangular subterranean bunker. The excavated space must be feet long, feet wide, and feet deep. If the earth-moving equipment removes soil at a rate of cubic yards per hour, how many hours will it take to complete the excavation?
- A270
- B90
- C18
- 10Cevap
Cevap
It will take 10 hours to complete the excavation.
The correct answer is . To find the time required, we must determine the total volume of the bunker in cubic yards, since the removal rate is given in cubic yards per hour. First, convert the dimensions from feet to yards by dividing by : the length is yards, the width is yards, and the depth is yards. The volume is cubic yards. Dividing the total volume of cubic yards by the rate of cubic yards per hour yields hours.
Adım Adım Çözüm
Anahtar Kavram
Converting linear dimensions to calculate volume in a specific unit, and using rates to find time.
Alternatif Yöntem
Instead of converting the linear dimensions first, you can calculate the volume in cubic feet (), convert the removal rate to cubic feet per hour (), and then divide: hours.