Zorluk: OrtaChange Management Processes

A network security administrator is preparing a formal change request to deploy a critical security patch to the enterprise central remote-access VPN gateway. The administrator has documented the purpose of the change, defined the scope of affected devices, specified the maintenance window, and conducted a comprehensive risk analysis. Before submitting the proposal to the Change Advisory Board (CAB) for review, which of the following mandatory components must the administrator add to complete the change request?

  1. A detailed rollback plan outlining step-by-step procedures to restore the gateway to its previous operational state if the patch failsCevap
  2. B
    An executive waiver allowing the technical team to bypass post-implementation testing in order to shorten the maintenance window
  3. C
    A formal end-user authorization agreement granting permission to skip CAB approval during emergency patch cycles
  4. D
    A request to perform primary patch validation directly on the production VPN gateway during active business hours

Cevap

A detailed rollback plan outlining step-by-step procedures to restore the gateway to its previous operational state if the patch fails
In standard ITIL and CompTIA change management processes, a formal change request must include the purpose, scope, risk assessment, implementation plan, and a documented rollback (backout) plan prior to CAB submission. The rollback plan ensures that if the patch introduces unexpected instability or connection failures, administrators can immediately restore the network service to a known operational state.

Adım Adım Çözüm

1
Analyze the existing change documentation
Identified that purpose, scope, maintenance window, and risk analysis are included, but rollback steps are missing.
CompTIA change management process mandates key components including purpose, scope, risk analysis, plan for change, rollback plan, end-user notification, and CAB approval.
2
Determine the required missing element for CAB submission
A rollback (backout) plan is required before CAB review.
CAB approval requires knowing how to safely undo a change if unexpected production failures occur.

Anahtar Kavram

Change Management Processes and Rollback Planning