A Linux administrator plans to apply a critical kernel patch to a web server during an upcoming scheduled maintenance window. The administrator has defined the scope of change and completed a risk assessment. Which of the following components must be included in the change request prior to submission for approval to ensure the system can be restored if the patch causes instability?
- A rollback plan detailing instructions to revert the server to its previous operating stateCevap
- BA chain of custody log detailing physical evidence handling procedures
- CAn immediate bypass request to skip Change Advisory Board review
- DAn incident escalation matrix for reporting active security breaches
Cevap
A rollback plan detailing instructions to revert the server to its previous operating state
A documented rollback plan is a required element of the change management process. It outlines clear, tested steps to reverse a change and restore services to a known good state if unforeseen errors occur during deployment.
Adım Adım Çözüm
Anahtar Kavram
Change Management Rollback Planning
Tahmini Süre:45s