A senior identity engineer is planning an operating system upgrade across primary Active Directory domain controllers in an enterprise network. Place the following change management procedures in the correct chronological order from first step to final step.
- 1Perform a comprehensive risk analysis and draft a detailed rollback plan.
- 2Submit the formal change request to the Change Advisory Board (CAB) for review and approval.
- 3Notify affected stakeholders and end-users of the scheduled maintenance window.
- 4Execute the domain controller operating system upgrade during the authorized maintenance window.
- 5Conduct post-implementation testing and update system configuration records.
Cevap
The correct order of change management steps begins with conducting a risk analysis and drafting a rollback plan, followed by submitting the request to the CAB for approval, notifying affected end-users of the scheduled maintenance window, executing the upgrade during the maintenance window, and concluding with post-implementation testing and documentation.
The standard CompTIA change management lifecycle follows a structured sequence: initial documentation (scope, risk analysis, and rollback plan), formal authorization by the Change Advisory Board (CAB), end-user notification of the scheduled maintenance window, implementation during the maintenance window, and post-implementation testing alongside final documentation.
Adım Adım Çözüm
Anahtar Kavram
CompTIA A+ Change Management Lifecycle Order