An IT technician is preparing a formal change request to upgrade the enterprise endpoint backup agent software across all corporate laptops. Before submitting the proposal to the Change Advisory Board (CAB) for review and authorization, which TWO of the following documentation elements must be included in the change request?
- A risk analysis evaluating potential network bandwidth saturation and operational impacts during deploymentCevap
- A detailed rollback plan outlining specific steps to restore the previous agent version if the installation failsCevap
- CA post-implementation audit report verifying that all laptops successfully completed their first updated backup cycle
- DA signed agreement from all end users confirming their individual consent to receive the software upgrade
Cevap
The change request documentation must include a risk analysis evaluating potential operational impacts and a detailed rollback plan to restore the previous agent version if deployment fails.
Formal change management procedures require that any proposal submitted to the Change Advisory Board (CAB) includes a comprehensive risk analysis to evaluate potential business or infrastructure impacts, as well as a documented rollback plan detailing procedures to revert system state if the deployment encounters critical failures.
Adım Adım Çözüm
Anahtar Kavram
Standard Change Management Documentation Requirements