A server administrator is planning a hypervisor deployment on a physical host workstation configured with 64 GB64\text{ GB} of RAM. The host operating system and hypervisor core require a baseline allocation of 8 GB8\text{ GB} of RAM, and organizational compliance requires reserving an additional 10%10\% of the total physical RAM for hypervisor dynamic overhead and host stability. If each planned guest virtual machine requires 5 GB5\text{ GB} of dedicated RAM, what is the maximum number of virtual machines that can be concurrently deployed on this host?

Cevap: 9 virtual machines

Cevap

The maximum number of virtual machines that can be hosted concurrently without exceeding host resource limits is 9.
Subtracting both host core memory (8 GB8\text{ GB}) and dynamic safety overhead (10%10\% of 64 GB=6.4 GB64\text{ GB} = 6.4\text{ GB}) leaves 49.6 GB49.6\text{ GB} of usable RAM for guest workloads. Dividing 49.6 GB49.6\text{ GB} by 5 GB5\text{ GB} per VM yields 9.929.92, which rounds down to 9 fully provisioned virtual machines.

Adım Adım Çözüm

1
Calculate the host dynamic overhead buffer
10%×64 GB=6.4 GB10\% \times 64\text{ GB} = 6.4\text{ GB}
Hypervisors require reserved memory overhead beyond the base operating system requirements to manage VM states safely.
2
Calculate total host RAM requirements
8 GB+6.4 GB=14.4 GB8\text{ GB} + 6.4\text{ GB} = 14.4\text{ GB}
Combines base host OS requirement with the mandatory dynamic buffer overhead.
3
Determine total remaining RAM available for guest virtual machines
64 GB14.4 GB=49.6 GB64\text{ GB} - 14.4\text{ GB} = 49.6\text{ GB}
Deduct host host dependencies from physical RAM capacity.
4
Calculate maximum VM count and floor to whole unit
49.6 GB/5 GB=9.92=9\lfloor 49.6\text{ GB} / 5\text{ GB} \rfloor = \lfloor 9.92 \rfloor = 9
Virtual machines cannot be provisioned partially; total memory allocation must be fully satisfied per instance.

Anahtar Kavram

Virtual Machine Memory Allocation & Host Overhead Capacity Planning
Tahmini Süre:1m 30s
Bu soruyu puanla