A network engineer is drafting a formal Request for Change (RFC) to update the configuration baseline and firmware of critical core switches in a financial datacenter. Which of the following elements must be included in the RFC documentation before submitting it for Change Advisory Board (CAB) review? (Select TWO.)
- A detailed rollback plan specifying clear metric triggers and procedures for reverting to the previous baseline if implementation issues occurCevap
- BAuthorization to bypass pre-implementation sandbox testing to minimize service disruption during production hours
- A defined maintenance window detailing the exact scheduled timeframe, affected network services, and expected business impactCevap
- DInstructions to downgrade device logging protocols to unencrypted SNMPv1 temporary credentials to accelerate post-change validation testing
Cevap
The essential RFC components are a detailed rollback plan with explicit failure triggers and a defined maintenance window specifying execution timeframes and business impact.
A formal Request for Change must include both an explicit rollback plan (with actionable triggers for reverting changes) and a scheduled maintenance window (defining the operational impact and exact time bounds). These elements allow the Change Advisory Board to assess operational risk accurately and ensure business continuity.
Adım Adım Çözüm
Anahtar Kavram
Request for Change (RFC) Essential Elements