A network technician is drafting a standard Request for Change (RFC) proposal to modify configuration parameters on a company's primary router. Which of the following key components must be included in the RFC document prior to submitting it for approval? (Select TWO.)

  1. A detailed rollback plan outlining steps to revert the configuration if the change causes unexpected outagesCevap
  2. A comprehensive risk and impact assessment evaluating potential service disruptions during implementationCevap
  3. C
    A differential backup restoration sequence detailing physical tape media sets needed for full system recovery
  4. D
    An immediate change execution step performed prior to establishing authorization or identifying probable cause

Cevap

A standard Request for Change (RFC) must include a detailed rollback plan to revert changes upon failure and a risk and impact assessment to evaluate potential service disruption.
A standard Request for Change (RFC) must include a detailed rollback plan to safely revert modifications if unexpected failures occur, alongside a comprehensive risk and impact assessment to evaluate how the change affects network availability and business operations.

Adım Adım Çözüm

1
Identify the mandatory components of formal IT change management documentation.
Standard RFC documentation requires a clear description of the change, business justification, risk/impact assessment, and rollback procedures.
The Change Advisory Board (CAB) needs complete information to assess operational risk before authorizing network modifications.
2
Evaluate the answer choices against RFC documentation requirements.
The rollback plan and the risk and impact assessment are mandatory inclusion items.
The rollback plan minimizes downtime during failed changes, while the impact assessment informs scheduling and approval decisions.

Anahtar Kavram

Request for Change (RFC) documentation elements