Prior to performing a major routing protocol modification on an enterprise core network, an engineer must submit documentation detailing how to undo the modifications should performance degrade. Which of the following change management elements fulfills this requirement?
- A rollback plan outlining explicit trigger conditions and step-by-step restoration proceduresCevap
- BA sequential media log for full and incremental data backup sets
- CA hypothesis testing protocol based on standard troubleshooting steps
- DA cryptographic SNMPv3 authentication profile configuration
Cevap
A rollback plan outlining explicit trigger conditions and step-by-step restoration procedures
A rollback plan is an essential component of change management documentation. It explicitly details the steps, commands, resources, and decision thresholds required to safely restore a network device or service to its previous stable configuration if a change fails or destabilizes the environment.
Adım Adım Çözüm
Anahtar Kavram
Rollback Plan in Change Management