A corporate enterprise plans to deploy a new port security baseline across all access switches at branch office sites during an upcoming scheduled maintenance window. Which of the following components MUST be included within the formal Request for Change (RFC) document prior to submitting it for Change Advisory Board (CAB) review? (Select TWO.)
- A comprehensive rollback plan detailing specific metric-based triggers and step-by-step instructions for configuration baseline restorationCevap
- BExecution of the proposed changes on live production access switches to capture benchmark telemetry prior to review
- A formal risk assessment outlining potential service impacts, dependency mapping, and business disruption severityCevap
- DA mandate requiring a full differential backup restoration of central network databases immediately upon change completion
Cevap
A comprehensive rollback plan detailing specific metric-based triggers and step-by-step instructions for configuration baseline restoration, and a formal risk assessment outlining potential service impacts, dependency mapping, and business disruption severity.
A formal Request for Change (RFC) must incorporate a comprehensive rollback strategy with predefined execution triggers and step-by-step recovery commands to restore the original baseline if issues arise. Additionally, a detailed risk assessment evaluating service dependencies and business impact is required so the Change Advisory Board (CAB) can properly evaluate and approve the change request.
Adım Adım Çözüm
Anahtar Kavram
Request for Change (RFC) essential documentation components