An enterprise organization is updating its continuity plan for a web server. The management team defines a requirement stating that, following an outage, data restored from backup must not be older than two hours. Which of the following business continuity parameters defines this maximum acceptable data loss timeframe?
- Recovery Point Objective (RPO)Cevap
- BRecovery Time Objective (RTO)
- CMean Time Between Failures (MTBF)
- DMean Time to Repair (MTTR)
Cevap
Recovery Point Objective (RPO)
Recovery Point Objective (RPO) dictates the maximum tolerable age of unrecovered data resulting from an interruption, which determines backup frequency.
Adım Adım Çözüm
Anahtar Kavram
Recovery Point Objective (RPO) vs. Recovery Time Objective (RTO)