Match each practical commercial event on the left with the correct legal principle governing contract discharge, vitiation, or remedy on the right.

  • A carrier fails to deliver raw cocoa beans to a confectionery company on the contractually scheduled date.Breach of contract
  • A seller untruthfully claims a commercial oven is fully operational to persuade a baker into buying it.Misrepresentation
  • A new government decree renders the export of timber illegal after a binding supply contract has been executed.Frustration
  • A carpenter builds half of a custom office cabinet before the buyer unjustifiably repudiates the agreement.Quantum meruit

Cevap

The failure to deliver raw cocoa beans on time corresponds to Breach of contract. The untruthful claim about the commercial oven corresponds to Misrepresentation. The new government decree making timber export illegal corresponds to Frustration. The claim for partial carpentry work executed corresponds to Quantum meruit.
The commercial events correctly match their legal concepts: failure of performance is a breach of contract; false statements inducing agreement constitute misrepresentation; supervening legal impossibility constitutes frustration; and claiming payment for partial work rendered is quantum meruit.

Adım Adım Çözüm

1
Analyze the failure to deliver raw cocoa beans by the scheduled date.
Identified as a failure of performance without lawful justification.
When a party defaults on a contractual obligation, the legal consequence is a breach of contract.
2
Analyze the false assertion made regarding the commercial oven's operational state.
Identified as a false statement of material fact inducing contract formation.
Misleading factual representations that induce agreement serve as a vitiating element known as misrepresentation.
3
Analyze the impact of a government decree making timber export illegal after agreement.
Identified as an external, unavoidable event making legal performance impossible.
Supervening legal impossibility without the fault of either party discharges the contract via frustration.
4
Analyze the carpenter's claim for half-completed cabinet work following wrongful repudiation.
Identified as an equitable remedy seeking payment proportional to work completed.
Quantum meruit provides compensation for the actual value of work performed when the contract is prematurely terminated by the other party.