Statement: Heavy rainfall has caused severe soil erosion along a section of a railway track passing through a hilly area, posing an immediate risk of track instability.

Which of the following proposed administrative courses of action logically follow from the given statement? Select all correct courses of action.

  1. Deploy an engineering team immediately to inspect the eroded slope and apply temporary reinforcement structures.Cevap
  2. Temporarily halt or divert train movement on the affected section until structural safety clearance is obtained.Cevap
  3. C
    Permanently decommission all railway lines across the entire hilly region to avoid future rain hazards.
  4. D
    Defer track inspection until the monsoon season concludes to minimize routine train delays.

Cevap

The logical courses of action are to immediately deploy an engineering team to inspect and temporarily reinforce the affected slope, and to temporarily halt or divert train traffic on the affected section until safety clearance is granted.
Both deploying an engineering team for slope inspection/reinforcement and temporarily halting or diverting train services directly address the immediate threat to public safety in a balanced, feasible, and effective manner.

Adım Adım Çözüm

1
Analyze the core problem in the statement
The problem is localized severe soil erosion threatening railway safety in a hilly area due to heavy rain.
Understanding the immediate threat determines which actions are proportional and relevant.
2
Evaluate immediate safety and corrective measures
Deploying engineers for slope inspection/reinforcement addresses the physical hazard directly. Pausing train traffic prevents disaster.
Valid courses of action must be feasible, immediate, practical, and prioritize public safety without introducing disproportionate harm.
3
Reject impractical or extreme proposals
Permanently shutting down the entire regional railway is overly drastic, while delaying inspection until monsoon end neglects urgent safety risks.
Actions that are overly punitive, extreme, or neglectful fail standard course of action criteria.

Anahtar Kavram

Evaluating practical, proportionate, and immediate administrative actions in crisis situations.