A systems engineer is preparing a change request to update the host hypervisor software across a cluster supporting mission-critical virtualized applications. The engineer has defined the scope of change, documented the business purpose, and completed a comprehensive risk analysis. Which of the following is the MOST critical required component that must be included in the change proposal prior to submitting it to the Change Advisory Board (CAB) for approval?
- A documented rollback plan specifying recovery procedures if the hypervisor update causes system failureAnswer
- BResults from post-implementation acceptance testing performed on live production cluster nodes
- CAuthorization to bypass CAB approval provided the update is scheduled during an off-peak maintenance window
- DPreliminary deployment of the update on a single live production host to evaluate stability
Answer
A documented rollback plan specifying recovery procedures if the hypervisor update causes system failure
Under standard IT operational procedures, a formal change proposal submitted for CAB evaluation must include the scope of change, purpose, risk assessment, and a documented rollback plan. The rollback plan ensures that technicians can quickly revert infrastructure to a functional state if the upgrade encounters unexpected faults.
Step-by-Step Solution
Key Concept
Change Management Process Documentation Requirements