A system administrator is preparing to apply a critical firmware update to the primary storage node hosting the organization's main Enterprise Resource Planning (ERP) database. The administrator has defined the scope of the change, performed a thorough risk analysis, created a tested backout plan, and secured approval from the Change Advisory Board (CAB). Which of the following actions must the administrator complete next before initiating the change during the scheduled maintenance window?
- Communicate the planned maintenance window and anticipated service downtime to affected business stakeholders.Answer
- BDeploy the update directly to the production ERP server immediately to test system stability under live load.
- CDiscard the documented rollback plan because formal CAB authorization supersedes the need for a recovery procedure.
- DConduct post-implementation functionality testing prior to applying the firmware package.
Answer
Communicate the planned maintenance window and anticipated service downtime to affected business stakeholders.
Communicating the maintenance window and service disruption details to affected end-users and stakeholders is a required change management procedure following CAB approval and prior to executing the change.
Step-by-Step Solution
Key Concept
Change Management Processes - End-User and Stakeholder Notification