Question

Difficulty: MediumWork Rate and Combined Work

A solar-powered desalination facility uses two purification units, Unit XX and Unit YY, to process standard batches of seawater. Working alone at its constant rate, Unit XX can desalinate a full batch of seawater in 1212 hours. Working alone at its constant rate, Unit YY can desalinate an identical batch of seawater in 1818 hours. Unit XX begins processing a batch alone and operates for 33 hours. Then, Unit YY is also turned on, and both units work together at their respective constant rates to complete the remaining portion of the batch. What is the total number of hours required to process the entire batch from the time Unit XX was first turned on?

  1. A
    5.45.4
  2. B
    7.27.2
  3. 8.48.4Answer
  4. D
    14.2514.25
  5. E
    25.525.5

Answer

8.4 hours
Unit X completes 1/12 of the batch per hour, so in 3 hours it processes 3/12 = 1/4 of the batch. This leaves 3/4 of the batch unfinished. Working together, Unit X and Unit Y have a combined rate of 1/12 + 1/18 = 5/36 batch per hour. Dividing the remaining 3/4 batch by 5/36 gives 27/5 = 5.4 hours for the joint operation phase. Summing the initial 3 hours and the 5.4 hours yields a total processing time of 8.4 hours.

Step-by-Step Solution

1
Calculate individual hourly work rates for each unit
Unit X rate = 112\frac{1}{12} batch/hour, Unit Y rate = 118\frac{1}{18} batch/hour
Work rate is the reciprocal of the time required to complete one full job.
2
Determine the fraction of work completed during the first 3 hours
Work completed by Unit X = 3×112=143 \times \frac{1}{12} = \frac{1}{4} of the batch
Unit X operates alone for 3 hours at a rate of 112\frac{1}{12} batch per hour.
3
Calculate the remaining fraction of work to be done
Remaining work = 114=341 - \frac{1}{4} = \frac{3}{4} of the batch
Subtract the completed fraction from the total job equal to 1 whole batch.
4
Find the combined hourly work rate of both units
Combined rate = 112+118=336+236=536\frac{1}{12} + \frac{1}{18} = \frac{3}{36} + \frac{2}{36} = \frac{5}{36} batch/hour
When entities work together, their individual rates add up.
5
Calculate the time required for both units to complete the remaining work
Time together = 34536=34×365=275=5.4\frac{\frac{3}{4}}{\frac{5}{36}} = \frac{3}{4} \times \frac{36}{5} = \frac{27}{5} = 5.4 hours
Time equals remaining work divided by combined rate.
6
Add the initial single-unit operating time to the combined operating time
Total time = 3+5.4=8.43 + 5.4 = 8.4 hours
The question asks for the total elapsed time from when Unit X first started.

Key Concept

Work Rate and Combined Work
Rate this question