Question

Difficulty: HardWork Rate and Combined Work

A municipal water treatment facility uses three pumps—Pump PP, Pump QQ, and Pump RR—to fill a main reservoir. Working alone at their respective constant rates, Pump PP can fill the reservoir in 20 hours, Pump QQ in 30 hours, and Pump RR in 40 hours.

All three pumps begin filling the empty reservoir simultaneously. After 4 hours, Pump PP shuts off. Pumps QQ and RR continue operating together for another 8 hours before Pump QQ is also shut off. Pump RR continues to run alone until the reservoir is completely filled.

How many total hours does it take to fill the reservoir from the start of the process until it is completely filled?

Answer: 16 hours

Answer

The total time required to fill the reservoir from start to finish is 16 hours.
Converting the individual completion times into work rates per hour (1/20, 1/30, and 1/40 of the reservoir per hour) allows us to determine the combined output per phase. In the first 4 hours, all three pumps fill 52/120 of the reservoir. In the next 8 hours, Pumps Q and R fill 56/120 of the reservoir. This leaves 12/120 (or 1/10) of the job remaining. Pump R, working at a rate of 1/40 per hour, takes 4 hours to complete the final 1/10. Adding all three durations (4 + 8 + 4) gives a total of 16 hours.

Step-by-Step Solution

1
Determine the individual hourly rates of work for each pump.
Pump P completes 120\frac{1}{20} of the job per hour, Pump Q completes 130\frac{1}{30} of the job per hour, and Pump R completes 140\frac{1}{40} of the job per hour.
Work rate is the reciprocal of the total time required to complete one whole task.
2
Calculate the work completed during Stage 1 (4 hours with all 3 pumps working).
Combined rate = 120+130+140=6+4+3120=13120\frac{1}{20} + \frac{1}{30} + \frac{1}{40} = \frac{6 + 4 + 3}{120} = \frac{13}{120}. Work done = 4×13120=521204 \times \frac{13}{120} = \frac{52}{120}.
Work done equals combined rate multiplied by time spent working together.
3
Calculate the work completed during Stage 2 (8 hours with Pumps Q and R working).
Combined rate of Q and R = 130+140=4+3120=7120\frac{1}{30} + \frac{1}{40} = \frac{4 + 3}{120} = \frac{7}{120}. Work done = 8×7120=561208 \times \frac{7}{120} = \frac{56}{120}.
Only Pumps Q and R are active during this second period.
4
Calculate the remaining fraction of work after Stage 1 and Stage 2.
Total work done so far = 52120+56120=108120=910\frac{52}{120} + \frac{56}{120} = \frac{108}{120} = \frac{9}{10}. Remaining work = 1910=1101 - \frac{9}{10} = \frac{1}{10}.
Subtracting completed work from the whole (1) leaves the remaining work to be completed.
5
Calculate the time required for Pump R to finish the remaining work alone.
Time = 1/101/40=4010=4\frac{1/10}{1/40} = \frac{40}{10} = 4 hours.
Time equals remaining work divided by the individual rate of Pump R.
6
Sum the time spent across all stages.
Total time = 4 hours (Stage 1)+8 hours (Stage 2)+4 hours (Stage 3)=164 \text{ hours (Stage 1)} + 8 \text{ hours (Stage 2)} + 4 \text{ hours (Stage 3)} = 16 hours.
The total elapsed time is the sum of the durations of each distinct phase.

Key Concept

Work Rate and Combined Work in Multi-Stage Processes

Alternative Method

Assume a convenient total reservoir volume equal to the least common multiple of the times: 120 units. Pump P produces 6 units/hr, Pump Q produces 4 units/hr, and Pump R produces 3 units/hr. Stage 1 (4 hrs): 4 × (6 + 4 + 3) = 52 units. Stage 2 (8 hrs): 8 × (4 + 3) = 56 units. Total filled = 108 units. Remaining = 12 units. Stage 3 (Pump R alone): 12 / 3 = 4 hrs. Total time = 4 + 8 + 4 = 16 hours.
Estimated Time:2m 0s
Rate this question