Question

Difficulty: MediumWork Rate and Combined Work

A commercial bakery has two industrial ovens, Oven A and Oven B. Working alone at its constant rate, Oven A can bake a full order of 1,8001,800 pastries in 66 hours. Working alone at its constant rate, Oven B can bake the same order in 99 hours. If Oven A begins baking the order alone and is joined by Oven B after 22 hours, how many total hours will it take from the time Oven A starts until the full order of 1,8001,800 pastries is baked?

Answer: 4.4 hours

Answer

The total time required to complete the entire order of pastries is 4.4 hours.
The total time of 4.4 hours is derived by determining Oven A's rate (1/6 job/hour) and Oven B's rate (1/9 job/hour). In the first 2 hours, Oven A completes 1/3 of the job, leaving 2/3. Operating together, their combined rate is 5/18 job/hour, which finishes the remaining 2/3 of the job in 2.4 hours. Summing 2 hours and 2.4 hours yields 4.4 total hours.

Step-by-Step Solution

1
Determine the individual work rates per hour.
Oven A completes 16\frac{1}{6} of the job per hour; Oven B completes 19\frac{1}{9} of the job per hour.
Work rate is the reciprocal of the total time needed to complete one full job.
2
Calculate the fraction of work completed during the first 2 hours by Oven A.
Oven A completes 2×16=132 \times \frac{1}{6} = \frac{1}{3} of the total job.
Work done equals rate multiplied by time spent working.
3
Find the remaining fraction of work to be done.
Remaining work is 113=231 - \frac{1}{3} = \frac{2}{3} of the job.
Subtract the completed fraction from 1 (the whole job).
4
Calculate the combined rate of Oven A and Oven B working together.
Combined rate is 16+19=318+218=518\frac{1}{6} + \frac{1}{9} = \frac{3}{18} + \frac{2}{18} = \frac{5}{18} job per hour.
When entities work together, their individual rates add up.
5
Calculate the time spent by both ovens working together to complete the remaining work.
Time together is 2/35/18=125=2.4\frac{2/3}{5/18} = \frac{12}{5} = 2.4 hours.
Time equals remaining work divided by the combined rate.
6
Calculate total time from the start.
Total time = 2+2.4=4.42 + 2.4 = 4.4 hours.
Add the initial single-agent work duration to the combined work duration.

Key Concept

Work Rate and Combined Work
Rate this question